      5. Process Areas
          5.17. Requirements Management
              SG 1 Manage Requirements
 SP 1.5 Ensure Alignment Between Project Work and Requirements 
Process AreaREQM
Level2
GoalSG 1
PracticeSP 1.5

Ensure that project plans and work products remain aligned with requirements.

This specific practice finds inconsistencies between requirements and project plans and work products and initiates corrective actions to resolve them.

Example Work Products

1.    Documentation of inconsistencies between requirements and project plans and work products, including sources and conditions

2.    Corrective actions

Subpractices

1.    Review project plans, activities, and work products for consistency with requirements and changes made to them.

2.    Identify the source of the inconsistency (if any).

3.    Identify any changes that should be made to plans and work products resulting from changes to the requirements baseline.

4.    Initiate any necessary corrective actions.



Process
Areas
(continuous)


Process
management  
 
OPF
 OPD
 OT  
 
OPP  
 OPM

Project
management
 
PP
 PMC 
 REQM 
 
SAM  
 
IPM
 RSKM
 
QPM

Engineering
 
RD 
 TS
 PI
 VER 
 VAL
Support
 
CM
 PPQA
 MA
 
DAR
 CAR