      4. Process Areas
          4.16. Risk Management
              SG 3 Mitigate Risks
 SP 3.2 Implement Risk Mitigation Plans 
Process AreaRSKM
Level3
GoalSG 3
PracticeSP 3.2

Monitor the status of each risk periodically and implement the risk mitigation plan as appropriate.

To effectively control and manage risks during the work effort, follow a proactive program to regularly monitor risks and the status and results of risk handling actions. The risk management strategy defines the intervals at which risk status should be revisited. This activity can result in the discovery of new risks or new risk handling options that can require replanning and reassessment. In either event, acceptability thresholds associated with the risk should be compared to the risk status to determine the need for implementing a risk mitigation plan.

Example Work Products

1.    Updated lists of risk status

2.    Updated assessments of risk likelihood, consequence, and thresholds

3.    Updated list of risk handling options

4.    Updated list of actions taken to handle risks

5.    Risk mitigation plans of risk handling options

Subpractices

1.    Monitor risk status.

After a risk mitigation plan is initiated, the risk is still monitored. Thresholds are assessed to check for the potential execution of a contingency plan.

A mechanism for monitoring should be employed.

2.    Provide a method for tracking open risk handling action items to closure.

Refer to the Work Monitoring and Control process area for more information about managing corrective action to closure.

3.    Invoke selected risk handling options when monitored risks exceed defined thresholds.

Often, risk handling is only performed for risks judged to be high and medium. The risk handling strategy for a given risk can include techniques and methods to avoid, reduce, and control the likelihood of the risk or the extent of damage incurred should the risk occur, or both. In this context, risk handling includes both risk mitigation plans and contingency plans.

Risk handling techniques are developed to avoid, reduce, and control adverse impact to work objectives and to bring about acceptable outcomes in light of probable impacts. Actions generated to handle a risk require proper resource loading and scheduling in plans and baseline schedules. This replanning should closely consider the effects on adjacent or dependent work initiatives or activities.

4.    Establish a schedule or period of performance for each risk handling activity that includes a start date and anticipated completion date.

5.    Provide a continued commitment of resources for each plan to allow the successful execution of risk handling activities.

6.    Collect performance measures on risk handling activities.




Process
Areas
(continuous)


Process
management
 OPD 
 
OPF 
 OPM
 OPP   
 
OT  
Project and work  
management 
 
CAM 
 IWM 
 QWM 
 REQM 
 RSKM 
 SAM 
 SCON 
 WMC 
 WP
Service establishment and delivery  
 IRP 
 SD
  
 SSD  
 SST  
 STSM 
Support 
 CAR 
 
CM 
 DAR 
 MA
 
PPQA