      5. Process Areas
          5.12. Project Monitoring and Control
              SG 1 Monitor the Project Against the Plan
 SP 1.4 Monitor Data Management 
Process AreaPMC
Level2
GoalSG 1
PracticeSP 1.4

Monitor the management of project data against the project plan.

Refer to the Plan Data Management specific practice in the Project Planning process area for more information about identifying types of data to be managed and how to plan for their management.

Data management activities should be monitored to ensure that data management requirements are being satisfied. Depending on the results of monitoring and changes in project requirements, situation, or status, it may be necessary to re-plan the project’s data management activities.

Example Work Products

1.    Records of data management

Subpractices

1.    Periodically review data management activities against their description in the project plan.

2.    Identify and document significant issues and their impacts.

An example of a significant issue is when stakeholders do not have the access to project data they need to fulfill their roles as relevant stakeholders.

 

3.    Document results of data management activity reviews.



Process
Areas
(continuous)


Process
management  
 
OPF
 OPD
 OT  
 
OPP  
 OPM

Project
management
 
PP
 PMC 
 REQM 
 
SAM  
 
IPM
 RSKM
 
QPM

Engineering
 
RD 
 TS
 PI
 VER 
 VAL
Support
 
CM
 PPQA
 MA
 
DAR
 CAR