 SP 2.3 Resolve Coordination Issues 
Process AreaIPM
Level3
GoalSG 2
PracticeSP 2.3

Resolve issues with relevant stakeholders.

Examples of coordination issues include the following:

· Product and product component requirements and design defects

· Late critical dependencies and commitments

· Product level problems

· Unavailability of critical resources or staff

 

Example Work Products

1.    Relevant stakeholder coordination issues

2.    Status of relevant stakeholder coordination issues

Subpractices

1.    Identify and document issues.

2.    Communicate issues to relevant stakeholders.

3.    Resolve issues with relevant stakeholders.

4.    Escalate to appropriate managers the issues not resolvable with relevant stakeholders.

5.    Track issues to closure.

6.    Communicate with relevant stakeholders on the status and resolution of issues.


 




Process
Areas
(continuous)


Process
management  
 
OPF
 OPD
 OT  
 
OPP  
 OPM

Project
management
 
PP
 PMC 
 REQM 
 
SAM  
 
IPM
 RSKM
 
QPM

Engineering
 
RD 
 TS
 PI
 VER 
 VAL
Support
 
CM
 PPQA
 MA
 
DAR
 CAR