      4. Process Areas
          4.9. Integrated Project Management
              SG 1 Use the Project’s Defined Process
 SP 1.1 Establish the Project’s Defined Process 
Process AreaIPM
Level3
GoalSG 1
PracticeSP 1.1

Establish and maintain the project’s defined process from project startup through the life of the project.

Refer to the Organizational Process Definition process area for more information about establishing organizational process assets and establishing the organization’s measurement repository.

Refer to the Organizational Process Focus process area for more information about deploying organizational process assets and deploying standard processes.

The project’s defined process consists of defined processes that form an integrated, coherent lifecycle for the project.

The project’s defined process logically sequences acquirer activities and supplier deliverables (as identified in the supplier agreement) to deliver a product that meets the requirements. The acquirer may require the supplier to align selected processes with the acquirer’s defined process.

The project’s defined process should satisfy the project’s contractual requirements, operational needs, opportunities, and constraints. It is designed to provide a best fit for project needs.

A project’s defined process is based on the following factors:

·         Stakeholder requirements

·         Commitments

·         Organizational process needs and objectives

·         The organization’s set of standard processes and tailoring guidelines

·         The operational environment

·         The business environment

Establishing the project’s defined process at project startup helps to ensure that project staff and relevant stakeholders implement a set of activities needed to efficiently establish an initial set of requirements and plans for the project. As the project progresses, the description of the project’s defined process is elaborated and revised to better meet project requirements and the organization’s process needs and objectives. Also, as the organization’s set of standard processes changes, the project’s defined process may need to be revised.

The project’s defined process is driven by the acquisition strategy. The acquirer’s defined process is affected, for example, by whether the acquisition strategy is to introduce new technology to the organization or to consolidate acquired products or services in use by the acquirer.

Example Work Products

1.    The project’s defined process

Example Supplier Deliverables

1.    Tailored supplier processes that interface with the acquirer’s defined process

Subpractices

1.    Select a lifecycle model from the ones available in organizational process assets.

Examples of project characteristics that could affect the selection of lifecycle models include the following:

·       Size or complexity of the project

·       Acquisition strategy

·       Experience and familiarity of staff with implementing the process

·       Constraints such as cycle time and acceptable defect levels

·       Clarity of requirements

·       Customer expectations

 

2.    Select standard processes from the organization’s set of standard processes that best fit the needs of the project.

3.    Tailor the organization’s set of standard processes and other organizational process assets according to tailoring guidelines to produce the project’s defined process.

Sometimes the available lifecycle models and standard processes are inadequate to meet project needs. In such circumstances, the project should seek approval to deviate from what is required by the organization. Waivers are provided for this purpose.

Tailoring can include adapting the organization’s common measures and specifying additional measures to meet the information needs of the project.

4.    Use other artifacts from the organization’s process asset library as appropriate.

Other artifacts can include the following:

·       Lessons learned documents

·       Templates

·       Example documents

·       Estimating models

 

5.    Document the project’s defined process.

6.    Conduct peer reviews of the project’s defined process.

Refer to the Acquisition Verification process area for more information about performing peer reviews.

7.    Revise the project’s defined process as necessary.



Process
Areas
(continuous)


Process
management   
 OPD
 OPF 
 OT  
 
OPP  
 OPM
Project
management  
 AM
 IPM
 
PP
 PMC 
 REQM
 
RSKM
 QPM
 SSAD
Acquisition Engineering 
 ARD

 ATM
 
 AVAL
 AVER

  
Support 
 CAR 
 
CM 
 DAR 
 MA
 
PPQA