      4. Process Areas
          4.7. Configuration Management
              SG 2 Track and Control Changes
 SP 2.1 Track Change Requests 
Process AreaCM
Level2
GoalSG 2
PracticeSP 2.1

Track change requests for configuration items.

Change requests address not only new or changed requirements but also failures and defects in work products.

Change requests can be initiated either by the acquirer or supplier. Changes that affect acquirer work products and supplier deliverables as defined in the supplier agreement are handled through the acquirer’s configuration management process.

Change requests are analyzed to determine the impact that the change will have on the work product, related work products, the budget, and the schedule.

Example Work Products

1.    Change requests

Example Supplier Deliverables

1.    Change requests

Subpractices

1.    Initiate and record change requests in the change request database.

2.    Analyze the impact of changes and fixes proposed in change requests.

Changes are evaluated through activities that ensure that they are consistent with all technical and project requirements.

Changes are evaluated for their impact beyond immediate project or contract requirements. Changes to an item used in multiple products can resolve an immediate issue while causing a problem in other applications.

The acquirer analyzes the impact that submitted change requests can have on supplier agreements.

Refer to the Solicitation and Supplier Agreement Development process area for more information about establishing the supplier agreement.

Changes are evaluated for their impact on release plans.

3.    Categorize and prioritize change requests.

Emergency requests are identified and referred to an emergency authority if appropriate.

Changes are allocated to future baselines.

4.    Review change requests to be addressed in the next baseline with relevant stakeholders and get their agreement.

Conduct the change request review with appropriate participants. Record the disposition of each change request and the rationale for the decision, including success criteria, a brief action plan if appropriate, and needs met or unmet by the change. Perform the actions required in the disposition and report results to relevant stakeholders.

5.    Track the status of change requests to closure.

Change requests brought into the system should be handled in an efficient and timely manner. Once a change request has been processed, it is critical to close the request with the appropriate approved action as soon as it is practical. Actions left open result in larger than necessary status lists, which in turn result in added costs and confusion.



Process
Areas
(continuous)


Process
management   
 OPD
 OPF 
 OT  
 
OPP  
 OPM
Project
management  
 AM
 IPM
 
PP
 PMC 
 REQM
 
RSKM
 QPM
 SSAD
Acquisition Engineering 
 ARD

 ATM
 
 AVAL
 AVER

  
Support 
 CAR 
 
CM 
 DAR 
 MA
 
PPQA