      4. Process Areas
          4.17. Project Planning
              SG 3 Obtain Commitment to the Plan
 SP 3.2 Reconcile Work and Resource Levels 
Process AreaPP
Level2
GoalSG 3
PracticeSP 3.2

Adjust the project plan to reconcile available and estimated resources.

To establish a project that is feasible, obtain commitment from relevant stakeholders and reconcile differences between estimates and available resources. Reconciliation is typically accomplished by modifying or deferring requirements, negotiating more resources, finding ways to increase productivity, outsourcing, adjusting the staff skill mix, or revising all plans that affect the project or its schedules.

During supplier selection and negotiation of the supplier agreement, the acquirer reconciles overall project work and resource levels based on proposals from the supplier. Following completion of the supplier agreement, the acquirer incorporates supplier plans at an appropriate level of detail into the project plan to support the alignment of plans. For example, an acquirer can incorporate major supplier milestones, deliverables, and reviews.

Example Work Products

1.    Revised methods and corresponding estimating parameters (e.g., better tools, the use of off-the-shelf components)

2.    Renegotiated budgets

3.    Revised schedules

4.    Revised requirements list

5.    Renegotiated stakeholder agreements



Process
Areas
(continuous)


Process
management   
 OPD
 OPF 
 OT  
 
OPP  
 OPM
Project
management  
 AM
 IPM
 
PP
 PMC 
 REQM
 
RSKM
 QPM
 SSAD
Acquisition Engineering 
 ARD

 ATM
 
 AVAL
 AVER

  
Support 
 CAR 
 
CM 
 DAR 
 MA
 
PPQA